Construction of an 8-inch underground gass pipeline from the Shadegan Booster Cluster to the Marun-3 Processing Unit.

In the field of Oil and gas

Place of execution:

Khuzestan Province - Ahvaz

Implementation time:

1403..1404

Contract amount:

851،925 Million

Project Manager:

Engineer Afshin Hatamvand

Construction of two underground 8-inch oil and gas transfer pipelines spanning the distance from the Shadegan Booster Cluster to the Marun-3 Production Unit, including cathodic protection stations and wellhead facilities.

Specifications:

  • Employer:

    National Southern Oilfields Company

  • Consultant: